Capability formulas and targets

Cp, Cpk, Cpm, Z and PPM formulas, with a Cpk to PPM table.

Cp (potential)
Cpk (actual, short term)
and use the same formulas with the overall standard deviation in place of .
Cpm (Taguchi)
is the target value.
Z and expected PPM

Within vs overall. (from , or ) shows what the process can do short term. s overall (the ordinary standard deviation) includes shifts between subgroups. A big gap between Cpk and Ppk means the process mean moves.

CpkExpected PPM if centeredUsual meaning
1.002,700Barely capable; 3σ each side
1.3366Common minimum for existing processes
1.507Typical requirement for some characteristics
1.670.54Common requirement for new processes and safety characteristics
2.000.002Six Sigma level (before the 1.5σ shift)

Always confirm stability (a control chart) and the distribution shape before trusting capability numbers. For skewed data use non-normal capability.