Capability formulas and targets
Cp, Cpk, Cpm, Z and PPM formulas, with a Cpk to PPM table.
Cp (potential)
Cpk (actual, short term)
and use the same formulas with the overall standard deviation in place of .
Cpm (Taguchi)
is the target value.
Z and expected PPM
Within vs overall. (from , or ) shows what the process can do short term. s overall (the ordinary standard deviation) includes shifts between subgroups. A big gap between Cpk and Ppk means the process mean moves.
| Cpk | Expected PPM if centered | Usual meaning |
|---|---|---|
| 1.00 | 2,700 | Barely capable; 3σ each side |
| 1.33 | 66 | Common minimum for existing processes |
| 1.50 | 7 | Typical requirement for some characteristics |
| 1.67 | 0.54 | Common requirement for new processes and safety characteristics |
| 2.00 | 0.002 | Six Sigma level (before the 1.5σ shift) |
Always confirm stability (a control chart) and the distribution shape before trusting capability numbers. For skewed data use non-normal capability.